Foundations and earthworks
Area of work

Foundations and earthworks

Setting out, excavation, rebar, concrete pile caps and industrial floors. In winter, admixtures and concrete heating.

Types
raft, piles, pile cap
Floors
industrial, load rated
Season
we work all year round
Scope of work

What the work includes

We run the whole project, from setting out to signed certificates. Nothing is subcontracted without your consent.

01

Surveying and setting out

We set out the grid, check levels and position the building on the plot.

02

Earthworks

Excavation, grading, compaction, backfill. Our own machinery.

03

Reinforcement

Rebar cages to the design, with cover and spacing checked.

04

Concreting

Concrete pile caps, rafts, pad and piled foundations.

05

Industrial floors

A reinforced slab with a hardened top, rated for load.

06

Waterproofing

Damp-proof course and coating where the ground and water table require it.

What it looks like

Projects in this area

Foundations and earthworks
Foundations and earthworks
Foundations and earthworks
Foundations and earthworks
Process

How the work goes

Lead times are for a standard building. The exact programme is fixed in the contract after the survey.

  1. Survey

    We look at the ground, water table and access

    1 day
  2. Estimate

    Type of base, scope of work and cost

    2–3 days
  3. Earthworks

    Excavation, hauling, compaction

    3–7 days
  4. Reinforcement

    Tying rebar, formwork, embedded plates

    3–5 days
  5. Pouring

    Concreting and curing

    1–2 days + curing
  6. Acceptance

    Geometry, levels, hidden-works certificates

    1 day
Transparency

What is in the price and what is extra

This is what the estimate looks like: half the site questions are settled before the contract.

Included in the price

  • Setting out
  • Earthworks with our own machinery
  • Formwork and rebar to the design
  • Concrete and its placement
  • Hidden works certificates

Priced separately

  • Geotechnical survey
  • Hauling soil beyond 5 km
  • Dewatering where the water table is high
  • Winter admixtures and concrete heating
  • Piled foundation on difficult ground

Where a building starts

A mistake in the ground costs more than anything else. So we start with setting out, look at the soil and water table, and only then choose the foundation.

Earthworks

Our own plant: excavator, tippers, compactors. Soil haulage and backfill are separate lines in the estimate, no surprises.

Concrete in winter

Anti-freeze admixtures, heating and strength monitoring. The programme grows honestly — and we say so in advance.

Questions

Questions about this service

If your question is not here, write to us and we will answer for your project.

How long does the concrete need to cure?

About 14 days before it takes the frame, full strength at 28 days. We often start erecting earlier by calculation.

What if the ground is weak?

We size piles or a raft, sometimes replace and compact the soil. The choice follows the ground survey, not guesswork.

Do you work in winter?

Yes, with anti-freeze admixtures and heating. We extend the programme honestly and put it in the contract.